A crane hired by a building construction company would be classified as (a) a financial cost (b) a direct manufacturing cost (c) an overhead cost (d) an administration cost

  • A. a financial cost
  • B. a direct manufacturing cost
  • C. an overhead costCorrect
  • D. an administration cost

Explanation

The crane supports construction but is not directly used to produce the building, so its cost is an overhead cost.