If 6 men can do a job in 4 days, how many days will it take 8 men to do the same job if they work at the same rate?

  • A. 2
  • B. 3Correct
  • C. 4
  • D. 6
  • E. 8

Explanation

6 × 4 = 24 man-days. 24 ÷ 8 = 3 days.