JAMB Accounting 2013 Objective — Question 29
Question 29 of 50 from the Joint Admissions and Matriculation Board (JAMB) Accounting 2013 Objective paper, with the correct answer and a full explanation.
Advertisement
In manufacturing account, the work-in-progress at the end of the year is
- A. deducted from the cost of goods completed during the yearCorrect
- B. added to the cost of goods completed during the year
- C. stated in the profit and account
- D. stated in the prime cost section
Explanation
Closing work-in-progress is deducted because it is not yet completed, while the opening work-in-progress is added because it relates to goods completed during the year.