Government proposed projects for 2013 fiscal year: I. Dam-Completed II. Road-Uncompleted III. Airport-Completed IV. Hospital-Uncompleted. From the information provided above, government opportunity cost would be

  • A. II only
  • B. I and II
  • C. I only
  • D. II and IVCorrect

Explanation

Based on the projects listed, only the Road and Hospital remain uncompleted - so the opportunity cost includes II and IV.