A contract terminated by the occurrence of an event which makes performance impossible is discharge by

  • A. breach
  • B. agreement
  • C. frustrationCorrect
  • D. performance

Explanation

A contract that becomes impossible to perform due to an unforeseen event is discharged by frustration.